What is the best way to detail or breakdown cabling activities, in MEP projects?

user-image
تم إضافة السؤال من قبل مستخدم محذوف‎
تاريخ النشر: 2016/04/11
Imran Ahmed
من قبل Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

The best way of breakdown for cabling is to consult the drawing electrical sections & detail and dscription of that item in BOQs.

The common breakdown is described below but it varies from project to project.

  1. Setting Out & Survey
  2. Excavation
  3. laying Electrical Pipes
  4. Laying Cable
  5. Laying cable tiles
  6. Foundation for light Fixtures
  7. Backfilling

Zain ul Abdin
من قبل Zain ul Abdin , Project Planning & Control Manager , Redco International Trading and Contracting

You mean the steps like:

  • arrival of cable in store
  • placement on rolls at site
  • laying of cable
  • termination of cable
  • final check

etc., or something else ?