ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

In the project management processes of initiating, planning, executing, monitoring & controlling and closing where would you place the QC and why?

user-image
تم إضافة السؤال من قبل Zain ul Abdin , Project Planning & Control Manager , Redco International Trading and Contracting
تاريخ النشر: 2016/04/22
Muhammad Mujtaba
من قبل Muhammad Mujtaba , Specialist File Processing , Jazz ( Mobilink )

Quality controll will be placed at Controlling and feedack segment

Mohamed Helal
من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

It could be in more than process  as initiating and of course executing,  as well as  on monitoring & controlling.

sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

Quality is vary important and it should be planned in planning process and should be assure during whole project specially while executing, but quality control is related to the product and it should be done after producing.

José Castilla
من قبل José Castilla , Manager , PDVSA

Quality control is applied from the start of a project with the conceptualization of a project engineering and the same applies to the completion of the project with the delivery of the Data Book of the work. This in the case of engineering projects and construction of facilities or infrastructure.

Sathish Prabhu.V
من قبل Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

I would always start quality with planning, because by doing so, we are inculcating quality at every stage of the project, so that execution, monitoring and control are completed as per targets. Building quality is more important than control and assurance.

Eugenio Noe Radovan III
من قبل Eugenio Noe Radovan III , Planning Engineer , Altorath International Engineering Consultants

QC should start on the initiation process since this is where how the company will follow the procedure and requirements of the project they are going to complete and show it to the client or any stakeholder that will benefit from the company's commitment.  The company has to show how quality control will be implemented from the execution up to closing of the project and such documentation is under the QC scope where you have to provide during initiation process.

Nelio Beleo
من قبل Nelio Beleo , Civil Inspector , Petrojet

QC is always involve in the processes of initiating, planning, executing and monitoring for the FF reasons:

1) initiating- QC are involved in the start up of the project cause they will prepare itp, QCP, procedures, review document submittals and etc.

2) planning - QC knows the stages of work

3) execution - They works on inspection, testing.

4) monitoring - controls quality records

 

مستخدم محذوف‎
من قبل مستخدم محذوف‎

QC has to be involved ab initio.

QC will be involved in:

  • Planning stage.
  • Design Stage.
  • Prototyping/Rapid Prototyping  Stage.
  • Execution Stage.
  • Post Execution stage.
  • Supply sourcing stage.

Mohammed Asim Nehal
من قبل Mohammed Asim Nehal , M Asim Nehal & Co , Chartered Accountants

Before every milestone...Put the QC

Eng Ahmed Elsharkawy
من قبل Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,,

i agree with experts answers

المزيد من الأسئلة المماثلة