ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Which input element to MRP specifies when to place an order? Select one:

a. Supplier Lead Time and Production Planb. Bills of material (BOM)c. Capacity Pland. All the above

user-image
تم إضافة السؤال من قبل Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG
تاريخ النشر: 2016/04/25
Omar Saad Ibrahem Alhamadani
من قبل Omar Saad Ibrahem Alhamadani , Snr. HR & Finance Officer , Sarri Zawetta Company

Thanks

I am sorry i have not enough experience in this field , i will wait with you for more answers

Ramzi SAMRI
من قبل Ramzi SAMRI , Industrial engineer , Institut für Betriebliche Bildungsforschung Berlin (IBBF)

Thank you 

Choose A, is the correct answer

Ahmed Mohamed Ayesh Sarkhi
من قبل Ahmed Mohamed Ayesh Sarkhi , Shared Services Supervisor , Saudi Musheera Co. Ltd.

 

Option " A "                                  .

Sathish Prabhu.V
من قبل Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Supplier lead time and production plan are the important elements in deciding when to place an order

Saiyid Maududi-Oracle Applications Consultant
من قبل Saiyid Maududi-Oracle Applications Consultant , Entrerprise Architect , US Technomatrix, Inc

Hello Team,

The information input into MRP systems comes from three main sources: a bill of materials, a master schedule, and an inventory records file. The bill of materials is a listing of all the raw materials, component parts, subassemblies, and assemblies required to produce one unit of a specific finished product. Each different product made by a given manufacturer will have its own separate bill of materials. The bill of materials is arranged in a hierarchy, so that managers can see what materials are needed to complete each level of production. MRP uses the bill of materials to determine the quantity of each component that is needed to produce a certain number of finished products. From this quantity, the system subtracts the quantity of that item already in inventory to determine order requirements.

The master schedule outlines the anticipated production activities of the plant. Developed using both internal forecasts and external orders, it states the quantity of each product that will be manufactured and the time frame in which they will be needed. The master schedule separates the planning horizon into time "buckets," which are usually calendar weeks. The schedule must cover a time frame long enough to produce the final product. This total production time is equal to the sum of the lead times of all the related fabrication and assembly operations. It is important to note that master schedules are often generated according to demand and without regard to capacity. An MRP system cannot tell in advance if a schedule is not feasible, so managers may have to run several possibilities through the system before they find one that works.

The inventory records file provides an accounting of how much inventory is already on hand or on order, and thus should be subtracted from the material requirements. The inventory records file is used to track information on the status of each item by time period. This includes gross requirements, scheduled receipts, and the expected amount on hand. It includes other details for each item as well, like the supplier, the lead-time, and the lot size.

Regards,

 

Saiyid

Nadeem Asghar
من قبل Nadeem Asghar , Supply Chain Consultant/Trainer , Independent Practitioner

My choice of right answer is  a. Supplier Lead Time and Production Plan

MUBARAK INAYTULLA KHAN
من قبل MUBARAK INAYTULLA KHAN , Procurement Manager , UNIT7 CONTRACTING EST. RIYADH.

 The answer for the above question goes to - A.

"A. Supplier Lead Time and Production Plan"

MADAN MOHAN GAJULA
من قبل MADAN MOHAN GAJULA , Material Coordinator , Sadara Chemical Company

a. Supplier Lead Time and Production Plan

مستخدم محذوف‎
من قبل مستخدم محذوف‎

The three main input sources to MRP are: a bill of materials, a master schedule, and an inventory records file. So BOM will be the answer

vidya sagar burra
من قبل vidya sagar burra , Assistant Manager SCM , Gati Kintetsu Express Private Limited

option a is the right answer..................

المزيد من الأسئلة المماثلة