What is the difference between the time avail-to do a job and the time required to do the job known as?

A.     event   

B.     float

C.     duration   

D.     constraint.

user-image
تم إضافة السؤال من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL
تاريخ النشر: 2016/04/25
Mohammed  Ashraf
من قبل Mohammed Ashraf , Director of International Business , Saqr Al-Khayala Group

Option "B" float could be considered the best among the available options. 

TARIG BABIKER AL AMIN
من قبل TARIG BABIKER AL AMIN , Head of Planning and Studies Unit , Sudanese Free Zones and Markets Co.

float or slack is the amount of time that a task in a project network can be delayed without causing a delay , so I think B

sameer abdul wahab alfaddagh
من قبل sameer abdul wahab alfaddagh , عضو هيئة تدريس , جامعة دلمون

This principle is developed by Frederick Taylor since 1911 is to determine the time to do the work on the basis of average worker after removing unnecessary movements and train workers perfected less time

Asim Ali Khalid
من قبل Asim Ali Khalid , Project Engineer , AHN Construction

Option "B" Float will be the correct answer of your question.

مها شرف
من قبل مها شرف , معلمة لغة عربية , وزارة التربية السورية

I leave the answer of professionals, thanks for the invitation. 

Amr Gamal Anwar Hassan
من قبل Amr Gamal Anwar Hassan , مهندس حاسب كميات , Shurfah Real Estate Development and Investment

my choice is Option "B" float

مستخدم محذوف‎
من قبل مستخدم محذوف‎

B. float...sometimes called slack, is the amount of time a project can be delayed from early start without changing the completion date. 

Eng Ahmed Elsharkawy
من قبل Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,,

 

my choice is option C

ghazi Almahadeen
من قبل ghazi Almahadeen , Project Facilitator , Jordan River Foundation

Thanks invite. ........... l think event 

sardar mardookhy
من قبل sardar mardookhy , Head of portfolio management department , MCI

I think float is the answer

Zain ul Abdin
من قبل Zain ul Abdin , Project Planning & Control Manager , Redco International Trading and Contracting

Difference between time available to do a job and time required to do a job is float. If more time is available, float is positive and if less time is avalable than required, float is negative.