ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Do the cost of software and cost of training for new software to implement 4D/BIM technology are considered the obstacle of adopting this technique?

user-image
تم إضافة السؤال من قبل Hussein Hamada , project manager , railway company and electrical projects
تاريخ النشر: 2016/05/07
SYED BADRUDDUZA
من قبل SYED BADRUDDUZA , Hydrographic Consultant , Shellhorn, Germany/ KS Consultant Bangladesh

Definitely

Definitely the Cost of software and cost of training for new software to implement 4D/BIM technology are considered the obstacle of adopting this technique, especially in developing & underdeveloped countries.

Abdullah Alshamrani
من قبل Abdullah Alshamrani

it is usually used in a large and complex project   , the cost is the main factor, it is costly to hire a team to visualize the sequence of events in the project in 4D (3D + time) in addition to the cost the software, 

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟