Do the cost of software and cost of training for new software to implement 4D/BIM technology are considered the obstacle of adopting this technique?

user-image
تم إضافة السؤال من قبل Hussein Hamada , project manager , railway company and electrical projects
تاريخ النشر: 2016/05/07
SYED BADRUDDUZA
من قبل SYED BADRUDDUZA , Hydrographic Consultant , Shellhorn, Germany/ KS Consultant Bangladesh

Definitely

Definitely the Cost of software and cost of training for new software to implement 4D/BIM technology are considered the obstacle of adopting this technique, especially in developing & underdeveloped countries.

Abdullah Alshamrani
من قبل Abdullah Alshamrani

it is usually used in a large and complex project   , the cost is the main factor, it is costly to hire a team to visualize the sequence of events in the project in 4D (3D + time) in addition to the cost the software, 