Buffer inventory is required as : (multiple answer)

A)

One or more stages in the operation cannot supply all the items it produces simultaneously

B)

Material cannot be transported instantaneously between the point of supply and the point of demand

C)

Compensation for the uncertainties inherent in supply and demand

D)

Compensation for differences in the timing of supply and demand

user-image
تم إضافة السؤال من قبل Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves
تاريخ النشر: 2016/05/08
Nitin Choudhary
من قبل Nitin Choudhary , Assistant Manager - Planning & Inventory Management , Green Planet Industries

C)

Compensation for the uncertainties inherent in supply and demand

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Due to uncertainty in demand

ADEL ACHOUR
من قبل ADEL ACHOUR , مدير مبيعات , SARL TUDOR ALGERIE

i think option c is more better here

sameer abdul wahab alfaddagh
من قبل sameer abdul wahab alfaddagh , عضو هيئة تدريس , جامعة دلمون

thanks for the invitationAnswer

C)

 

Compensation for the uncertainties inherent in supply and demand

MADAN MOHAN GAJULA
من قبل MADAN MOHAN GAJULA , Material Coordinator , Sadara Chemical Company

C)   Compensation for the uncertainties inherent in supply and demand  ======== is the right answer

dalal alharbi
من قبل dalal alharbi

I apologize for the answer I leave the answer to the experts, specialists in this field that's not my specialty field.

Wasi Rahman Sheikh
من قبل Wasi Rahman Sheikh , Warehouse Supervisor , AL MUTLAQ FURNITURE MFG

Right answer option C<<<<<<<<<<<<<<<<<<<<<<,,

Ahmed Mohamed Ayesh Sarkhi
من قبل Ahmed Mohamed Ayesh Sarkhi , Shared Services Supervisor , Saudi Musheera Co. Ltd.

Options " C & D "                     .

ghazi Almahadeen
من قبل ghazi Almahadeen , Project Facilitator , Jordan River Foundation

thanks invite. ............ answer c

Sathish Prabhu.V
من قبل Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Right answer is A, B and D, because we need buffer inventory for stages, for delay in transport and timing difference in supply and demand. 

We cannot plan buffer for uncertainties in supply and demand.