أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
1- take tap point fromt the existing manhole
2- take tap point from pipes that came outside buildings
3- use slop 1%
4- every 15 m make manhoe
5-the invert level for pipes depending on the entry and exist of pipe to manhole
how many in day , how much % every hour, how big % of dirty , where to go next(them self or by pumps, or pipe)