ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You are working with a highly experienced technical team; each member has a minimum of 15 years experience...

 You are hosting a meeting for the team to discuss the best way to move forward with the project from a technical standpoint. There are number of different requirements that have been discussed, however one of the team members is behaving like a heckler - making fun of ideas he thinks are not viable or telling people flat-out that they're wrong. This is beginning to disturb some of the other

team members who have started to visibly disengage from the meeting. You ask this individual what the problem is and he responds, “Who died and put you in charge?” Once the meeting adjourns, you pay a visit to this team member’s manager and are prepared to write-up this individual for insubordination. However what is probably the real problem?

See below options for answer

a. Lack of a work breakdown structure

b. Absence of the requirements traceability matrix

c. No project charter

d. A flawed scope baseline

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/05/13
مستخدم محذوف‎
من قبل مستخدم محذوف‎

c. No project charter

is the correct answer.

And the real problem of PM authority should be addressed first in project charter, so that the team members can recognize the PM authority.

Eng Ahmed Elsharkawy
من قبل Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option C

Mohamed Helal
من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

Thanks for invitation....I endorse answers given by colleagues &Experts

sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

Option C>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C – The first part of the question is a red herring. The issue is that the team member doesn’t recognize the

PM’s authority. This would have been addressed in the project charter

المزيد من الأسئلة المماثلة