When performing the scope control process, which of the following statements is correct? Which following option is correct?

a. Scope control validates the delivered scope for the project

b. The work performance measurements produced are part of the PMIS

c. The inspection process is a key tool and technique used in scope control

d. Scope control is performed in concert with other control processes

 

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/05/14
مستخدم محذوف‎
من قبل مستخدم محذوف‎

d. Scope control is performed in concert with other control processes

Ahmed Mohamed Ayesh Sarkhi
من قبل Ahmed Mohamed Ayesh Sarkhi , Shared Services Supervisor , Saudi Musheera Co. Ltd.

apologize i'm not expert on this field

 

Eng Ahmed Elsharkawy
من قبل Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option D

Mohamed Helal
من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

Thanks for invitation....I endorse answers given by colleagues &Experts

dalal alharbi
من قبل dalal alharbi

I apologize for the answer I leave the answer to experts of specialists in this area this is not the field of specialist.

ACHMAD SURJANI
من قبل ACHMAD SURJANI , General Manager Operations , Sinar Jaya Group Ltd

a. Scope control validates the delivered scope for the project