The project management plan, validated deliverable, requirements documentation, and requirements traceability matrix are all considered...

 REFER TO BELOW OPTIONS FOR ANSWER

a. Outputs of the scope control process

b. Inputs to the validate scope process

c. Inputs to define scope process

d. Tools and techniques of the scope verification process

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/05/14
sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

All answers are not related except B option, although the validated deliverable differ from verified deliverable and verified deliverable should be as input

Thank you

Oussama BEN SMIDA, PMP
من قبل Oussama BEN SMIDA, PMP , Senior Construction Manager , Havelock One Interiors

Option B - Inputs to Validate Scope Process but to rectify validated deliverables by verified deliverables  which's the ouput of Control quality process. 

You can refer to PMBOK 5th Edition

dalal alharbi
من قبل dalal alharbi

I apologize for the answer I leave the answer to experts of specialists in this area this is not the field of specialist.

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

I think option B is appropriate regarding to the project. 

Mohamed Helal
من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

Thanks for invitation....I endorse answers given by colleagues &Experts

Ahmed Mohamed Ayesh Sarkhi
من قبل Ahmed Mohamed Ayesh Sarkhi , Shared Services Supervisor , Saudi Musheera Co. Ltd.

apologize i'm not expert on this field

 

Eng Ahmed Elsharkawy
من قبل Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option B