أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
a. Both activities have to finish at the same time
b. The predecessor has to finish before the successor can finish
c. Both activities are on the critical path
d. The predecessor has a defined lead while the successor has a defined lag
No.B .............. a Successor Activity cannot finish until a Predecessor Activity has finished
thanks for invition ,,,,,,,,,, my choice is option A
Agree on expert answers. Thanks
a. Both activities have to finish at the same time
Both activites have to finish at same time irrespective of their start dates.
I agree with A option...........
A is the correct answer ...........
B - This is the definition of a finish to finish relationship: I must complete activity ‘a’ before I complete
Activity ‘b’