أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
a. You have decided that fast tracking is the best option to pull in the schedule by three weeks
b. You have decided that crashing the schedule is the best option to pull in the schedule by three weeks
c. Your project has negative float
d. You cannot deliver the project three weeks earlier without impacting project quality
Agreed with you,
......Thanks
Answers is
c. Your project has negative float
Negative float of 3 weeks
Thanks for invitation....I endorse answers given by colleagues &Experts
C – Notice the question doesn't ask you what you will do about it – it simply asks you ‘what does this
mean’? What it means is that your project now has a negative float of three weeks
thanks for invition ,,,,,,,,,, my choice is option C