The project schedule has finally been completed for the project. In reviewing the resource estimates, you?

notice that several key resources have been assigned multiple activities on several parallel network paths. You have also noticed that the resources for the different time phases vary greatly, sometimes as much as %.What scheduling technique would be the best to use at this point?

a. Critical chain

b. Critical path

c. Monte Carlo

d. Resource leveling