ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

What is the primary difference between critical path (CPM) and critical chain (CCPM) schedule approaches?

 

a. There is fundamentally no difference

b. CPM focuses on managing float while CCPM focuses on managing buffers

c. CCPM focuses on extensive multi-tasking while CPM focuses on resource leveling

d. CPM uses heuristics while CCPM uses mathematical modeling

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/05/16
sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

B is teh answer,

Thanks for invitation

مستخدم محذوف‎
من قبل مستخدم محذوف‎

b. CPM focuses on managing float while CCPM focuses on managing buffers

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B – By definition, critical path method focuses on managing float while the critical chain project

management method focuses on managing buffers. Answer ‘A’ is incorrect, and answers ‘C’ and ‘D’ are red herrings

Ghada Eweda
من قبل Ghada Eweda , Medical sales hospital representative , Pfizer pharmaceutical Plc.

A correct answer is already given by experts. Thanks

المزيد من الأسئلة المماثلة