a. There is fundamentally no difference
b. CPM focuses on managing float while CCPM focuses on managing buffers
c. CCPM focuses on extensive multi-tasking while CPM focuses on resource leveling
d. CPM uses heuristics while CCPM uses mathematical modeling
B is teh answer,
Thanks for invitation
b. CPM focuses on managing float while CCPM focuses on managing buffers
B – By definition, critical path method focuses on managing float while the critical chain project
management method focuses on managing buffers. Answer ‘A’ is incorrect, and answers ‘C’ and ‘D’ are red herrings