ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Two of your junior project managers in the PMO are having a disagreement about the meaning of earned value...

 The first project manager is arguing that earned value is the dollarized amount of the work actually completed; the second project manager is arguing that the earned value actually represents the amount of money that the work is supposed to cost within a given time frame, and when that work is completed, you have earned that much value. While you are listening to the argument unfold, a stakeholder on their project approaches them and tells both project managers that the original basis of estimate was less accurate than a rough order of magnitude. How does this information mostly likely impact earned value calculations?

a. It makes no difference. They are still tracking work completed and there are dollars associated with the completed work

b. Variances have little meaning when the basis of estimate is flawed or covers too wide a range. Earned value calculations may misrepresent the occurrence of actual variances

c. The only impact may occur when calculating estimate at completion or estimate to completion. Variances may occur up to%

d. You must start at the end of the project and work backwards to derive the correct earned value calculations due to the ranginess of the basis of estimate

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/05/18
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B – If the basis of estimate is a fiction, then your variances are also a fiction. Earned value or calculations work only when there is a solid bottom-up estimate or historical data on which to base the estimate. The estimator needs to know what the work is supposed to cost in order to compute accurate earned value

Ramon Bayon
من قبل Ramon Bayon , Private practice , Private practice

"Variances have little meaning when the basis of estimate is flawed or covers too wide a range. Earned value calculations may misrepresent the occurrence of actual variances".

It's just the same as if the scope is not done well...then the project doomed to fail.

Eng Ahmed Elsharkawy
من قبل Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

I apologize for the answer,,,,,,,,,,,,,,,,,I leave the answer to experts specialists in this field ...l can't understand your question?BUT,,,,,,,,,,,,,

the PMo can have a supporting role for PMs and also for teaching them.

plus it can follow the Organization goals achieving among with projects and programs.

Wasi Rahman Sheikh
من قبل Wasi Rahman Sheikh , Warehouse Supervisor , AL MUTLAQ FURNITURE MFG

Wait for more experts answer <<<<<<<<<<<<<<<,

المزيد من الأسئلة المماثلة