أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
completion (BAC) is $,. AC = $,. The SPI =1.2. What is the CPI of this project? (Round to2
decimal places)
a.1.
b.1.
c.1.
d. It cannot be determined from the information given
C – This is a two-part calculation. You must first derive earned value from the SPI formula; SPI = EV/PV. At this point you know SPI (1.2) and PV ($60,000). Thus solving for EV you get: EV = 1.2 * $60,000 = $72,000. You can now compute CPI = EV/AC or $72,000/$65,000 = 1.11
Agree with experts answer <<<<<<<<<<<<<<<<<,,
the answer is therer but the numbers in question is missed
I think some numbers/figures are lost?