أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
While the work is proceeding according to plan, some of the stakeholders are not satisfied with the work delivered to date, even though it meets requirements specifications. You have held several meetings with the stakeholders to try to get to the root cause of the problem. With some of the technical team present at these meetings, it becomes obvious that some of the stakeholders have had great difficulty in
describing what they want. As a result, some of the delivered product doesn't meet stakeholder expectations. Currently your CPI is1.3 and the SPI is .. What is your largest concern right now?
a. Clarifying the requirements collection process
b. The schedule
c. Managing stakeholder expectations
d. An increasing probability that some technical team members may leave the project due to high levels of frustration with stakeholders
thanks for invition ,,,,,,,,,, my choice is option C
correct answer is C >>>>>>>>>