ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

CPI is 1.2, SPI is 1.1. Four months later CPI is.91 and SPI is .86. The most likely reason for this change is?

 

a. The project manager has not been keeping track of variances on the project to implement corrections

b. As work packages were being executed, discovery on critical path activities caused estimates to

change drastically on several of the work packages

c. The WBS was inaccurate

d. Several key stakeholders insisted on a last-minute scope change

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/05/18
Muhannad AlHaj Issa
من قبل Muhannad AlHaj Issa , Group IT Manager , Jordanian For Investment & Transportation

Scope creep would be the most common Factor. 

Ibrahim Noureldin
من قبل Ibrahim Noureldin , Division Financial Manager/Controller , M.C. DEAN

Several key stakeholders insisted on a last-minute scope change

LIYAO LI
من قبل LIYAO LI

Which statement about change requests is not true?

Sethumadhavan krishnan
من قبل Sethumadhavan krishnan , Personnel Affairs Supervisor , Saudi Catering & Contracting

When you sell or produce on certain costing work it requires to use high or low priced goods. So it is a. accounting estimates

Wasi Rahman Sheikh
من قبل Wasi Rahman Sheikh , Warehouse Supervisor , AL MUTLAQ FURNITURE MFG

Agree with experts answer <<<<<<<<<<<<<<<<<<<<<<,,,,

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B – Significant changes in earned value, such as the one described, usually point to some kind of discovery on the project, especially since the product was sailing along smoothly until it appeared to hit a bump. Answer ‘A’ is highly unlikely as is answer ‘C’. Changing scope at the last minute would also force a change request which may cause a re-baseline of the project. This would not necessarily change its CPI or SPI

sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

I think "A" option..........

المزيد من الأسئلة المماثلة