ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Which performance index describes the cost projection of the remaining work that must be achieved to meet the goals of the project?

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/05/18
Imran khan, PMP
من قبل Imran khan, PMP , Project Engineer/ Project Manager LV/LC , Engineering Consultants Group (ECG)

CPI is the cost performance index that tells you what is the status of the project, while TCPI would give you the performance index at the completion of the project therefore you are right! its a definition to TCPI. A

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A – This is a definition of the To Complete Performance Index (TCPI)

sardar mardookhy
من قبل sardar mardookhy , Head of portfolio management department , MCI

C option,

Thanks for invite...

المزيد من الأسئلة المماثلة