In terms of progress reporting, when do project activities earn value?

a. As soon as the activity begins

b. Only after the activity has completed

c. According to the earned value accrual rules set up by the project manager

d. Determined by the Configuration Control Board in your organization

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/05/18
ZULFIQAR ALI
من قبل ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

The formula for Earned Value = % of completed work X BAC. As soon activity start earning progress we can start progress reporting.

My answer is A. As soon as the activity begins

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Only after the activity has completed

Joey Balanquit
من قبل Joey Balanquit , Planning Engineer , Mott MacDonald

a. As soon as the activity begins.

 Because as soon as the activity begins different type of resources also being utilized.

مستخدم محذوف‎
من قبل مستخدم محذوف‎

c. According to the earned value accrual rules set up by the project manager