ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You have just reviewed the most recent audit from the quality assurance organization which has identified an out-of-control process...

You call the members of the technical team in for an emergency meeting to address the situation, as this is a critical process in your development effort. Analyzing an out of control situation for remediation occurs in which process and results in the creation of?

a. Perform quality assurance and project management plan updates

b. Perform quality control and change requests

c. Perform quality assurance and change requests

d. Perform quality control and validated changes

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/05/25
sardar mardookhy
من قبل sardar mardookhy , Head of portfolio management department , MCI

I think C is the answer,..

Thanks

Eng Ahmed Elsharkawy
من قبل Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option C

Mohamed Helal
من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

b. Perform quality control and change requests

omama salih
من قبل omama salih , Salesman , Special Gift house

C is the correct answer was

Sathish Prabhu.V
من قبل Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Once a NCR for out of control of a process is identified, next step is to control it, do necessary changes to bring back it to control limits. Hence right answer is Option B, Perform Quality Control and Change requests.

المزيد من الأسئلة المماثلة