ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Decisions as to the types of projects that should be accomplished and strategic plans as to the quality of the projects that are required should be the decision of which of the following?

 are required should be the decision of which of the following?

a. Project manager b. Procurement manager c. Upper management d. Stakeholders

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/05/27
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Suresh Kumar option C is correct

Sathish Prabhu.V
من قبل Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Upper management decides the Project and the strategic plans

sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

Option C.........

Thanks.......................

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Option C  seems to be the appropriate answer.

Mohamed Helal
من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

..............c. Upper management...........

Usman Islam
من قبل Usman Islam , Logistics And Warehouse Manager , Kirtanlal Scaffolding & Formwork

option A in my opinion would be the correct asnwer

Eng Ahmed Elsharkawy
من قبل Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option C

Ksenija Kancelak
من قبل Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

I think the answer is:

c. Upper management

المزيد من الأسئلة المماثلة