The quality manager of a company wishes to analyze the data that is coming to him in the form of a list of defects that have occurred?

in the shipping department. The report comes with defects listed chronologically as they occurred, the cost of the repair necessary to correct each defect, the person involved, and a description of the defect. The manager would like to determine which of the defects should be corrected first according to the frequency of the defect occurring. He should use which of the following quality tools?

a. Cause and effect diagram b. Sampling inspection c. Pareto diagram d. Quality critical path

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/05/27
Sathish Prabhu.V
من قبل Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Obviously it should be Pareto analysis from the given options, because it prioritizes the order of action

Usman Islam
من قبل Usman Islam , Logistics And Warehouse Manager , Kirtanlal Scaffolding & Formwork

Paretto diagram... option C 

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Pareto Diagram is the correct answer.

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Pareto diagram shows the defects patterns

sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

C .....pareto diagram,,,,

Thanks

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Agree with the answers for Option C. Pareto diagram