ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

As a project manager you decided to reduce one test cycle. During the acceptance testing the customer...

reported more than the expected no. of defects. This forced you to send an additional resource to customer location for stabilizing the system. The cost associated with this additional effort is best described as:

A.  Lost value

B.  Opportunity cost

C.  Cost of non-conformance

Contingency

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/06/07
sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

I think C is the answer,

Cost of non conformance

Hrvoje Kancelak
من قبل Hrvoje Kancelak , Certificated Traffic Engineer , Office of independent engineer

The answer is definitely:

 

C.  Cost of non-conformance

Mohamed Helal
من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

I prefer to leave answers to Experts. Thanks for Your kind Invitation.

Ksenija Kancelak
من قبل Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

I think the answer is:

B. Opportunity cost

 

Farhana Siddique Fari
من قبل Farhana Siddique Fari , Coordinator , Coordinator at DFA, Dr Fazeela Abbasi, Advanced Skin, Laser & Hair Institute, Islamabad.

Thank you so much Mr. Farooq for your kind invitation; I prefer awaiting the Experts' answers.

مستخدم محذوف‎
من قبل مستخدم محذوف‎

B. Oppurtunity Cost is the correct answer.

Details:

Opportunity costs: When you focus on Project A, it generally means that resources are not available to work on Project B. The lost value of Project B is Project A's opportunity cost.

Sathish Prabhu.V
من قبل Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Opportunity cost is the cost of lost value when another action taken to counter previous action

Eng Ahmed Elsharkawy
من قبل Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option C