the quality manager utilising the data from related industries and checking if the current project is performing acceptably. Which of the following tool best suitable for this?
A. Design of experiments
B. Flowcharting
C. Benchmarking
D. Control Chart
Benchmarking is the apt answer since the manager is comparing related industries data
My oppinion is that the right answer is:
C. Benchmarking
The catch phrase of "related industries" sways the answer towards Option C.
I agree, option C is the correct answer