ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You are the project manager of a company that is building ATM software for a large bank and financial institutions.?

You have been told that the ATM software must meet very stringent quality

standards. Including rigorous auditing of all transactions, ability to recover in case

of software/ hardware errors, and fraud detection and analysis. In order to ensure that these quality standards are met, you've invested heavily in proper training of your project staff, instrumented numerous design review and rigorous performed quality planning. Which of the following best describes the cost associated with you project?

A. Prevention costs

B. Failure costs

C. Appraisal cost

D. Rework cost

E. Defect cost

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/06/13
Ramzi SAMRI
من قبل Ramzi SAMRI , Industrial engineer , Institut für Betriebliche Bildungsforschung Berlin (IBBF)

As I know, A is the good answer. Thanks

Sathish Prabhu.V
من قبل Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Prevention cost is the most apt answer for the subject question where Project manager looks to build a robust ATM software

Usman Islam
من قبل Usman Islam , Logistics And Warehouse Manager , Kirtanlal Scaffolding & Formwork

in my opinion, option A is the best choice.

sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

My option is A. preventing costs

Thanks

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. Prevention costs is the most suitable answer

Mohamed Helal
من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

I prefer to leave answers to Experts. Thanks for Your kind Invitation.

Ksenija Kancelak
من قبل Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

My oppinion is that the answer is:

A. Prevention costs

kamal purbia
من قبل kamal purbia , IT Project Manager , Automated Systems Company

Preventive costs are

1. Training

2. document processes

3. equipment

4. time to do it right

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Correct answer is 

A. Prevention costs