أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
A. Quality Assurance
B. Quality Control
C. Quality Planning
D. Quality Review
Monitoring results against standards are called QUALITY CONTROL.
B. Quality Control...............
it is a process of Quality control
where the characteristics of the product is monitored to assure that it comply the requirements
Thanks, b is the good answer.
My opinion is that the right answer is:B. Quality Control
It is B - Quality Control . This is the process through which project results or product is measured and determined whether they comply with quality standards.
Correct answer is
B. Quality Control
Thanks for invitation
----------------B. Quality Control--------------------
B. Quality Control
Quality Control (Assurance and Audit are part of quality control activities)
Quality Control is the apt answer and is part of Quality Assurance.