Cost of quality includes: -?

 

A. Cost of all work to build a product or service that conforms to the requirements

B. Training programs

C. Cost of all work resulting from nonconformance to the requirements

D. a and b

E. all of the above

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/06/18
مستخدم محذوف‎
من قبل مستخدم محذوف‎

Answer E seems to be the closest answer.

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Thanks for invitation -

With the choice E. all of the above-

Its mean All operational costs include since the beginning of production and even marketing with all experiments (active and inactive).

Waleed Elbasyouni PMP®
من قبل Waleed Elbasyouni PMP® , Senior Project Control Engineer , azmeel contracting company

E. all of the above 

Cost of  conforms and Cost of nonconformance and Training programs 

 

مستخدم محذوف‎
من قبل مستخدم محذوف‎

E. all of the above

thanks for invitation

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Cost of Quality means the total cost expected & worked out to meet Project or Service or Product quality. It comprises A ) Appraisal Costs ; B )  Prevention Costs;  C ) Failure Costs which includes both Internal & External Costs .  

Alaa Mohamed Abdallah
من قبل Alaa Mohamed Abdallah , Plant Manger , IEC (ALDAWLIA) iec-egypt.com

E

Cost of quality = cost of good quality + cost of bad quality

cost of good quality = training + awareness+ product approval documentations +.....

cost of bad quality = rework cost + scrap cost+ complaint cost +....

Ramzi SAMRI
من قبل Ramzi SAMRI , Industrial engineer , Institut für Betriebliche Bildungsforschung Berlin (IBBF)

Thanks, E is the suitable answer.

Sathish Prabhu.V
من قبل Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

All costs including training comes under cost of quality hence right answer is option E - All of above

Uday Wani
من قبل Uday Wani , Senior Project Engineer , Daleel Petroleum LLC*

COQ is mainly dived into 2 parts

Cost of Conformance and Cost of Non-conformance

sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

E. all of the above

thanks,..