The project charter should be issued by?

 

A. The project manager

B. Client requesting services

C. Manager external to project

D. Manager internal to the project

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/06/25
ZULFIQAR ALI
من قبل ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

The project charter must be issued by someone external to the project team and at the appropriate organizational level to satisfy the needs of the project.

Ksenija Kancelak
من قبل Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

My opinion is that the right answer is:

C

sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

C. Manager external to project...

Usman Islam
من قبل Usman Islam , Logistics And Warehouse Manager , Kirtanlal Scaffolding & Formwork

Option B...........................

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Thanks for invitation -

With the choice - C.

Eng Ahmed Elsharkawy
من قبل Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

 

thanks for invition ,,,,,,,,,, my choice is option C

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

In my opinion Answer should be B & C.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Appropriate answer is option C. Manager external to project

VINAY KUMAR GOSWAMI
من قبل VINAY KUMAR GOSWAMI , Partner , 2MI

Ans: B Client Requesting Service

By definition project charter should be issued by the Project Sponsor. Hence the option A and D are ruled out.

C is possible only when that manager is initiator of the project. But it is not mentioned in the response.

Hence option B is only possible option that fulfill the criteria of 'Project Sponsor'. Please note that word 'Client' can be used for other functional unit requesting project services. Hence it is not necessary that 'Client' is always external to the organization. 