Within your project records management systems, you would document and archive all of the following procurement related documents except?

 

A.  Statement of Work 

B.  Proposal 

C.  Negotiation Process 

D.  Seller's marketing material related to the contracted work   

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/07/02
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The most suitable answer is option C:  Negotiation Process 

sardar mardookhy
من قبل sardar mardookhy , Head of portfolio management department , MCI

C. is the right answer...

thanks.........

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Exactly C.  Negotiation Process . is the correct answer.

As negotiation process is not documented.

Thanks for invitation

Usman Islam
من قبل Usman Islam , Logistics And Warehouse Manager , Kirtanlal Scaffolding & Formwork

Option D ................................

mamoun mokhtar
من قبل mamoun mokhtar , general manager , albyan technical foungary

opurchasing orders and contracts

Mohamed Helal
من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

 

C.  Negotiation Process.......................

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Answer is C .

Normally, Negotiation Process is not archieved while closing the procurement.

 

Ksenija Kancelak
من قبل Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

My opinion is that the right answer is:

C. Negotiation Process 