Who has to prepare Method Statements at Site? Construction Team or QA QC Department?

user-image
تم إضافة السؤال من قبل Sanju Plavilaputhenveedu , Sr. QA / QC Engineer , Al Jaber Energy Services LLC
تاريخ النشر: 2016/07/03
Moidheensha pokakkillath
من قبل Moidheensha pokakkillath , Nexcon Development and construction , Nexcon development and construction

Site construction team will be preparing the method statement and the QA QC will be reviewed before submission.

SankaraSubramanian arunachalam
من قبل SankaraSubramanian arunachalam , Construction Manager , Cengiz General Constructions of Buildings Roads Bridges and Sewerage S.P.C.

METHOD STATEMENT SHOULD BE PREPARED BY CONSTRUCTION TEAM AND VERIFIED BY PLANNIG DEPARTMENT

Jayadevan  Nair
من قبل Jayadevan Nair , Piping Welding Inspection Engineer , Fluor Consultancy Netherlands BV Kuwait

Method statement will be prepared by the construction team with the help of engineering department and Quality and Safety will review and suggest required correction and include omissions if any.

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Method Statements are elaborate documents prepared.These cover the complete methodology of work at site.It is prepared by Construction Team and vetted/cleared for acceptance by QC/QA.

julius cesar dumaplin
من قبل julius cesar dumaplin , QA/QC Engineer , Flora Boring Excavating Contracting LLc

Method Statement is prepared by QA/QC as per material approval, project specification and requirements and site construction team will implement on site.

NAPOLEON SANTOS
من قبل NAPOLEON SANTOS , SENIOR CIVIL ENGINEER (QAQC, MATERIAL, PROJECT ENGINEER, ESTIMATOR) , TECHNO HOME CONSTRUCTION

The Construction Team to be reviewed by the QAQC Department.

 

karthick palanisamy
من قبل karthick palanisamy , Civil Engineer (Site Engineer) , Hassanesco trading &contracting W.L.L

QALQC Engineers should prepare method statements of all works in the site

Rehan Raja
من قبل Rehan Raja , Architect , Abdullah

Construction Team coordination with QA/Qc 

Fahad Khan
من قبل Fahad Khan , Senior QA/QC Engineer , Ruwad Civil Construction

QA/QC Department has to prepare Method statment for site team 

Syed Moullimuddin
من قبل Syed Moullimuddin , senior Mechanical Engineer , vision Construction company

The construction team should prepare method statement at Site and QA/QC should review this and get approval to work.

hatem labib
من قبل hatem labib , Quality control manager , MISER consultant

QA/QC responsible for preparing method of statements, site construction team responsible for implementation.   