By using cost to cost method (% of completion), but it need a loads of attention. The linchpin of attention lies in the following
Total actual cost incurred to date & total recent estimated cost to date, from which % of completion is being calculated
Contract value and its variations
Certified cost and uncertified cost ( as delivery of material deemed uncertified cost, even though its money is received but that should be taken away from actual cost incurred,) , because the percent of completion is based on work done cost, not delivery of materials.
all parties payments are revenues and after deducted suppliers demand then balance amount of calaculated gp
It depends on your revenue recognition policy.
mainly you have 2 ways
1, cost recovery
2, percentage of completion
Note: you should use one method for your all contracts.