You are the project manager for an upcoming outdoor concert event. You're working on the procurement plan for the computer software program that?

 

will control  the lighting and screen projections during the concert. You're comparing the cost of purchasing a software product to the cost of your company programmers writing a custom software program. You are engaged in which of the following?

A. Using expert judgment

B. Make-or-buy analysis

C. Procurement planning

D. Creating the procurement management plan

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/07/16
kasule henry
من قبل kasule henry , access engineer/Net work , Sombha solutions store

B. Make-or-buy analysis because it is an upcoming

Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

I would like to select B as my answer.

Ksenija Kancelak
من قبل Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

My opinion is that the answer is B

Ahilan R
من قبل Ahilan R , Scientific Assistant-D , Nuclear Power Corporation of India Ltd (NPCIL)

B. Make-or-buy analysis  is the correct answer

Hassan El Debbes
من قبل Hassan El Debbes , Managing Director / Marketing Manager , Alarabiya Advertising Co. / Alarabiya Electrical Co.

The answer is B. Make-or-buy analysis.

 

مستخدم محذوف‎
من قبل مستخدم محذوف‎

B. Make-or-buy analysis : Very important exercise which unfortunately many organizations don't do. Mandatory to be done to identify opportunity costs. 

Ravichandran CSCP
من قبل Ravichandran CSCP , Supply Chain Consultant & Trainer , Freelancer

Make-or-buy analysis while it was customized software

Joan Galimon
من قبل Joan Galimon , Workers , Rebisco Biscuits Corporation

C.Procurement Planning,ofcourse you need to do that first.

Abu Bakar Siddique
من قبل Abu Bakar Siddique , Procurement / Purchase Executive , Younone sports shoes Ind. LTD.

D. Creating the procurement management plan

 

IMRAN ALI KHAN Imran
من قبل IMRAN ALI KHAN Imran , Business Development Executive , Interlink Communication Private Limited

The best suitable answer for the question is Option ''A'' which is Expert Judgments. In expert one get to know with alot of opinions regarding an issue of the project due to which we can cover Make or Buy Analysis and remaining two steps as well.. Regards

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The most suitable option is

B. Make-or-buy analysis