Fixed-price contracts place more risk on the -?

A. contractor and seller

B. contractor

C. seller

D. owner

E. All of the other alternatives apply.

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/07/22
Terrence Walmsley
من قبل Terrence Walmsley , Owner , The Awesome Group of Companies

Both parties. If the negotiated price impacts negatively on the supplier margins, they will look to ways to recover costs.

Contracts should be viewed as an extension of the company business with the contracted suppliers as a business partner. 

Fixed price contracts should be short term allowing both parties opportunity to review pricing and allow for comfortable exchange of business.

Ksenija Kancelak
من قبل Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

The right answer is: 

B and C