ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Which of the following represents the reason why post-contract evaluations are important?

 

A. The contract fee is contractor performance related.

B. It establishes a historical base for contractor selection.

C. It acts as a point of reference for making legal procurements.

D. Most contracts make them a necessity.

E. They are legally required in many jurisdictions.

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/07/22
Ksenija Kancelak
من قبل Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

The right answer is:        B

Ahilan R
من قبل Ahilan R , Scientific Assistant-D , Nuclear Power Corporation of India Ltd (NPCIL)

B. It establishes a historical base for contractor selection. 

in technical as well as financial capability

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The most suitable option is

B. It establishes a historical base for contractor selection

Abdul Rehman
من قبل Abdul Rehman , Electrical Engineer , Tamdeed Projects

My answer to this question is option B

Abhay Khajuria
من قبل Abhay Khajuria , Senior Operations and Vendor Manager , Edureka

Thanks for the opportunity provided to attemp such a good Question.

Option D & E as these are very subjective.

However, post contract evaluation is very important and vital for all the first three reasons as the outcome can assist the management contract team with following information which is very important in decision making :-

Supporting Option A : To find out if the deliverables are matched by the contrator or not ? This will guage the performance of the contractor and help the team to decide the full & final formalities (Settlement of final bills, release of retention money and issue of performance/completion certificates).  

Supporting Option B: The evaluation report will also help the contract team in formulating future contract policy or approach that may require some improvisation in processes, terms or specification. 

Supporting Option C: The evaluation report helps the contract/project managers in highlighting grey areas where the contractor has breached any of the terms or specification.Which then acts as a point of reference for making legal procurements.