The most important is how and at what margins you tendered and got award , the early you highlighted the missing client requirement which will be there always is most important challenge , next is fastest vendor and critical equipment approval as tendered SO your procurement back up must be strong.
mobalization is next and most important challenge and then comes the special request of milestone dates recovery for lost time in tendor
Too many...
Starting with engineering
- to determine the exact intention of the customer, to offer the best solutions and to find the most favorable compromise between available funds, available utility resources(power, water, etc) and the output of the plant
- to accurately determine the challenges of civil works, since they may heavily impact costs.
- to accurately split procurement procedures between LLIs and SLIs
- to find the best compromise between reliability and cost of subcontractors
- to find a proper commissioning procedure and to do it accurately.
I may have omitted some others, but I preferred to stick to the general issues, and not enter in details, which may have lead to a whole scientific work