Which of the following would least likely to be found as part of a contract?

 

A. Roles of responsibilities, pricing and payments

B. Independent estimates, evaluation criteria

C. Statement of work, schedule

D. Inflation adjustments, acceptance criteria

E. Warranty, limitation of liability

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/07/30
Nadjib RABAHI
من قبل Nadjib RABAHI , Freelancer , My own account

The answer is :

B : Independent estimates, evaluation criteria

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

It is B - Independent estimates, evaluation criteria. These are the tools to draw a contract.

Imran Ahmed
من قبل Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-D Inflation adjustments, acceptance criteria

Normaly this is not part of contract.