The contract management plan is an output of which process?

 

A. Select sellers

B. Plan purchases and acquisitions

C. Plan contracting

D. Contract administration

E. Request sellers

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/08/06
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The best option given in show details is

A. Select sellers

appa anand badipetla
من قبل appa anand badipetla , Deputy Manager-Designs , PES ENGINEERS PVT Ltd

Plan Contracting  :  As per PMI its Procurement management plan

Nadjib RABAHI
من قبل Nadjib RABAHI , Freelancer , My own account

A: select sellers

C: plan contracting

D: contract administration 

Mihaela Kovacheva
من قبل Mihaela Kovacheva , Organizational Manager , Baumax Bulgaria Ltd /Part of Baumax AG/

The contract management plan is a part of the procurement lifecycle. Its purpose is to help the professionals manage contracts and it starts before the contract is signed.