ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

The administrative closure procedure that is an output of the close project process includes all of the following EXCEPT?

A. Verify all deliverables have been provided and accepted

B. Validate exit criteria have been satisfied

C. Close all contracts associated with the completed project

D. Define stakeholders approval requirements for changes

E. Confirm that the project has met sponsor and stake holder's requirements

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
تاريخ النشر: 2016/08/14
Ghaith Khasskhoussy
من قبل Ghaith Khasskhoussy , Production Engineer , CIMINTER

The answer for this question is D

Kingsley Gomez
من قبل Kingsley Gomez , Instrumentation , BAPCO

D is the answer for the asked question.

مستخدم محذوف‎
من قبل مستخدم محذوف‎

D, as this answer is not applicable as this will be applicable before the project ends

Rahul Patil
من قبل Rahul Patil , Senior Project Manager , Oracle

Option 'C' is not an output of the close project process. Stakeholder Management Plan or RACI is defined in the Project Management Plan which is at the begining of the project and not at the time of Closure.

Hamza Ferchichi
من قبل Hamza Ferchichi , tutor , YOULEARN ACADEMY

The best option is

C. Close all contracts associated with the completed project because Administrative Closure: ... Product acceptance is carried out using the Close Project or Phaseprocess.

Muhammad Farooq
من قبل Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co

The best option is

C. Close all contracts associated with the completed project

Imran Ahmed
من قبل Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-D Define stakeholders approval requirements for changes

المزيد من الأسئلة المماثلة

هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟