An Item rate contract is beneficial to client or one job contract?

user-image
تم إضافة السؤال من قبل Hiren Budhwani , Senior Engineer , Alchemy Real Estate
تاريخ النشر: 2016/08/14
Anwar warsi
من قبل Anwar warsi , Engineer Contracts , SAADULLAH KHAN & COMPANY

The item rate contract is beneficial for both the client and the contractor, because the actually executed work is measured and paid. More over the extra items of work are easy to identify and some missed items necessarily executed between the given items activities can also be proved and evaluated whereas in one job this is not possible.

Hiren Budhwani
من قبل Hiren Budhwani , Senior Engineer , Alchemy Real Estate

Item rate for detailed RA and Negotiation section wise