ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

According to FIDIC ,Do we have EOT ;if there is increment in the quantities more than the original in contract? Please mention to the reference.

user-image
تم إضافة السؤال من قبل Sameh Zaher (transferable iqama) , Planning ;Time and Cost Management Bsc,PM Diploma , Big construction company
تاريخ النشر: 2016/08/18
Imran Ahmed
من قبل Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Yes EOT can be claimed if there is an increament in the quantities as compared to original contract.

Please refer to following Sub-clause in FIDIC

1) Sub-Clause-8.4 (Extension of Time)

2) Sub-Clause-.3 (Variation Procedure)

3) Sub-Clause-.1 (Contractor's Claims)

المزيد من الأسئلة المماثلة