ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

What is the first action you have to start with, after the engineering step in the project management?

user-image
تم إضافة السؤال من قبل Walid Mohammad Abusabha MSc Engr PMP RMP LSSGB NASP PMO and PMC , MEP Manager , WSP
تاريخ النشر: 2016/08/20
مستخدم محذوف‎
من قبل مستخدم محذوف‎

Thank you for the invitation.

Many steps needs to be taken. You need to determine:

  • The cost of execution for the project.
  • The duration required for completion.
  • What are the needed equipment.
  • What are the material required.
  • What about the human capital or labour required.
  • Is it better to contract sub-contractors to excute some parts of the project and is it cost efficient.

Then you need to combine all these points into an efficient execution plan.

Kapil Sharma
من قبل Kapil Sharma , General Manager Projects , CBRE

Development of master plan which consists of procurement plan, execution plan, resource plan, cost plan, audit/inspection plan etc.

ahmad haidar ahmad
من قبل ahmad haidar ahmad , Technical Manager , Al Massela Engineering and construction

the second step is to prepare the procurement schedule

Emmanuel Wamweta
من قبل Emmanuel Wamweta , production supervisor , Tembo Steel Rolling

I fully agree with the experts submissions here regarding this matter.

Thanx forvthe invitation

مستخدم محذوف‎
من قبل مستخدم محذوف‎

I believe that once the engineering part is done it's followed by the Project Close-out Phase. This phase consists of the following.

1. Post Implementation Review

2. Performance review

3. Lessons Learned

4. A final Project Evaluation

5. Delivery of Final Documentation

6. Project Sign-Off

7. Customer Satisfaction Survey

Waqas Khan
من قبل Waqas Khan , Advisory Consultant , Grant Thornton Abu Dhabi

After engineering step I will evalute the protype on test envoironment

Nadjib RABAHI
من قبل Nadjib RABAHI , Freelancer , My own account

The main issues that must be addressed for the successful completion of a project are related to time and cost. We must, first estimate the likely duration of the project and the organizing way to minimize its cost and its duration (so that the resources committed are as short as possible and that it can become operational as soon as possible) .

المزيد من الأسئلة المماثلة