ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You are currently the project manager for a software development project, developing a next generation data-mining tool?

 Your team is developing a new software product that will help customers better manage large volumes of data, especially for data reporting purposes. Midway through the project your customers has asked you to add additional reporting functionality to the software, specifically to correlate sales data across multiple geographic regions based on time. The functionality was NOT part of the original project plan. This is an example of which of the following?

A. Scope creep

B. Fast tracking

C. Gold plating

D. Inadequate project planning

E. Crashing the schedule

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/08/20
Imran Ahmed
من قبل Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-C Gold plating is the answer

asber shaabo
من قبل asber shaabo , ادارة -محاسبة - متابعة شؤون الفندق لدى القطاع العام و الخاص , فندق عينكاوة باﻻص - فندق ارابيﻻ غراند -نقابة محامي كردستان العراق

Professional experts and developers must be acquired to deal with software and security vulnerabilities

DR MD ANWAR HOSSAIN
من قبل DR MD ANWAR HOSSAIN , Moderator , bayt.com

I think A - option is proper answer.

المزيد من الأسئلة المماثلة