Which of the following statements about fast-tracking is TRUE?

A. Fast tracking is the process of increasing the schedule by overlapping various project tasks.

B. One of the advantages of fast-tracking is that it can often lead to reduced rework and reduces project risks.

C. None of the statements are true

D. Fast tracking refers to assigning additional resources to a project in an attempt to decrease project schedule/ timeline.

E. Fast tracking involves performing activities sequentially

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/08/21
Muhammad Farooq
من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The most suitable option is 

C. None of the statements are true

Alia Al Darmaki
من قبل Alia Al Darmaki , Internship , Abu Dhabi Investment Authority

D Because A means where skipping tasks, and B is wrong

mohamed sabbah
من قبل mohamed sabbah , Planning & Projects Control Manager , I.E.M.S.A. Construction

D. Fast tracking refers to assigning additional resources to a project in an attempt to decrease project schedule/ timeline.

ahmmed Shahid Bolar RMP PMP  BE
من قبل ahmmed Shahid Bolar RMP PMP BE , Senior planning and Scheduling Engineer , Dar Al Handasah

Right Answer is Option E.

Option A is wrong: Fast Track decreases schedule

Option B is Wrong: Doesnt reduce rework or reduce risk, May Increase Risk

Option D is wrong: Adding resousre is called crashing

 