أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
of a-story office building. This project will use three point estimates to calculate the estimates for activity duration. You have the following estimates for task A (creating the foundation). Assuming the triangular distribution what is the average duration estimate based on the following three point estimates?
Pessimistic= days
Optimistic= days
Most likely= days
A.
B..6
C..4
D..3
E..
Some information are missing