أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
A) Project Management Team will request the Client to terminate the Contractor.
B) Project Management Team will instruct the Consultant/Engineer to issue NCR against the Contractor's works to make sure QA/QC requirements.
C) Project Management Team will deduct some percentage(%) from Contractor's Monthly progress Invoice.
D) Project Management Team will warn the contractor and allow him to continue works to complete project on time.
Thanks for invitation -
They follow D - C - A Step by Step !!!
B-Issuing an NCR by the consultant/Engineering (The authorized PM by the sponsor and customer) and circulate the appropriate incharges depts.(Procurements and financial) to deduct a monthly percentage amount of the contractor monetary funding (funding requirements to complete project objectives) based upon the contractual and legal obligation on the agreements and the list the contactor in the non-prequalified vendors. By the way there is a sum lump money allocated for the project's formal closure can deduct a certain amount if the vendor failed to meet the customer final requirements and expectations based upon the legal binding relationship .
make B,D,C and A respectively.
they first audit as for sop,and if it not full filled than they can take carrect stape for taht,agenst that .
IT WILL GOOD TO FOLLOW THE PLAN B
Project Management Team will deduct some percentage(%) from Contractor's Monthly progress Invoice.
i am agree with experts...........
The quality assurance team can continuously inspect and write the required reports and recommendations.
If a contractor fails to meet QA/QC requirements, the following project management team members typically make decisions:
This team evaluates the situation and determines appropriate corrective actions, which could range from warnings to contract termination.