You are in process of analyzing the effects of identified risks. Which of the following is the LEAST helpful input?

 

A. Risk register

B. Project scope statement

C. Project cost management plan

D. Risk management plan

E. Performance reports

F. Project schedule management plan

 

Answer: E

 

 

 

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/08/28
Mohamed Helal
من قبل Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

Option # E........but i saw wrongly you have shown the correct answer.

Numan Sadiq
من قبل Numan Sadiq , Credit Analyst , Dubai Islamic Bank

E. Performance reports.

You have answered the question by yourself, If I am not wrong.

 

Ahmad Taha
من قبل Ahmad Taha , IT Project Manager , malomatia

You are in process of analyzing the effects of identified risks. Which of the following is the LEAST helpful input?

E                                                                                                                                                                 

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invitation.

Answer is E - Performance reports.

Next step after identifying risks is to do Qualitative & Quantitave analysis of the identified risks for which performance reports are not required.

 

 

Ismail Fararjeh
من قبل Ismail Fararjeh , PCB Engineer , High Tech Talents

In my opinion it would be project scope statement which is the least one that effect not ( e ) and that is very obvious for alot of project managers because identified risks could not been effect by scope statements

ahmed el-hagrasy
من قبل ahmed el-hagrasy , Costing Head , Golden Africa Djibouti

the least helpful input is  Project scope statement