أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
A. Risk register
B. Project scope statement
C. Project cost management plan
D. Risk management plan
E. Performance reports
F. Project schedule management plan
Answer: E
Option # E........but i saw wrongly you have shown the correct answer.
E. Performance reports.
You have answered the question by yourself, If I am not wrong.
Thanks for the invitation.
Answer is E - Performance reports.
Next step after identifying risks is to do Qualitative & Quantitave analysis of the identified risks for which performance reports are not required.
the least helpful input is Project scope statement