ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You’re managing a project, when you and the seller both agree that you need to have the seller add more resources to the project in order?

 to finish on time. The number of resources is written into the contract. What’s the BEST way to proceed?

A. Your project will be late because you can’t change the contract once it’s signed

B. You need to convince the buyer to sign a new contract

C. You need to use the contract change control system to make the change to the contract

D. You need to use claims administration to resolve the issue

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/09/04
Faisal Ali Syed
من قبل Faisal Ali Syed , Payments & Reconciliation Officer , United Bank Limited

Option C is best choice that is to make changes in contract.

mamoun mokhtar
من قبل mamoun mokhtar , general manager , albyan technical foungary

 

when there is a delay in delivery -  when the cost is high compared to other sources  - when the material supplied is out of specifications  or not genuine-

Saifeddine CHARIF
من قبل Saifeddine CHARIF , Marketing Manager/ Office Manager , Arrow Motors Company AMC

The customer desire to add more resources means he didn't commit to the conditions of the contract since the resources are already mentioned and agreed on. Accordingly a change in the terms/conditions of the contract must be applied

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invitation.

Option C is the answer. Change control system is used to make changes to the contract that is in progress.

Ghulam Farid
من قبل Ghulam Farid , Contracts Officer , Abu Dhabi Company for Onshore Petroleum Operations (ADCO)

Option C as any change in da scope should be a partb of contract for vwhich you need to raise variation order or amendment in da contract

Imran Ahmed
من قبل Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-C

You need to use the contract change control system to make the change to the contract

المزيد من الأسئلة المماثلة