As a Project Manager on replacing 2 miles of sewer pipe part of your job is to determine if there are changes to the scope of the project?

the schedule, the budget and the technical requirements. These responsibilities are part of which process:

A. Executing

B. Controlling

C. Planning project management

D. Closing

user-image
تم إضافة السؤال من قبل Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
تاريخ النشر: 2016/09/10
مستخدم محذوف‎
من قبل مستخدم محذوف‎

B. Controlling............

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Contract document shall be read to understand if the same is in scope or not. If ambiguity is there, project manager shall raise concern flag and / or change order, at the earliest opportunity, so that clarity is established before execution with or without a change order.

Imran Ahmed
من قبل Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-B Controlling...............

Mohammed Asim Nehal
من قبل Mohammed Asim Nehal , M Asim Nehal & Co , Chartered Accountants

b) Controlling is the correct answer.

Jose Frazao
من قبل Jose Frazao , Professor Graduate Level ( Postgraduate ) , University of Carabobo

C.  those procedures belongs to planning phase. 

Darryl Cole
من قبل Darryl Cole , Business Manager , Advanced Metal Curving Pty Ltd

i think these belong in C)