أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
A. The estimated total cost of the project when done
B. Allocating the cost estimates to the individual work items
C. Estimating the cost of the resources needed to complete project activities
D. The sum of the approved cost estimate
Option (B) -----------------------
A. The estimated total cost of the project
C. Estimating the cost of the resources needed to complete project activiti
The explanation given for cost are very closer. However, the item D. gives a clear picture as it is the estimate that has been approved.
B. Allocating the cost estimates to the individual work items